Free Calculator

Draw Schedule Calculator

Enter your construction budget and see it broken into a 35-line milestone draw schedule — a common category structure for a single-family build, with a dollar amount for each phase. Edit any percentage to match your actual project.

$
100.0% allocated — balanced
#Line item% of budgetDraw amountCumulative
Draw 01 — Foundation & Site Work · 15%
1Site work & grading
%
$9,0003.0%
2Footings
%
$9,0006.0%
3Foundation / slab
%
$27,00015.0%
Draw 02 — Framing & Rough-In · 25%
4Framing — walls
%
$18,00021.0%
5Framing — roof
%
$12,00025.0%
6Roof decking & sheathing
%
$9,00028.0%
7Roofing (materials & install)
%
$9,00031.0%
8Windows
%
$6,00033.0%
9Exterior doors
%
$3,00034.0%
10House wrap & exterior sheathing
%
$6,00036.0%
11HVAC rough-in
%
$6,00038.0%
12Plumbing rough-in
%
$3,00039.0%
13Electrical rough-in
%
$3,00040.0%
Draw 03 — Drywall & Mechanicals · 25%
14Low-voltage / structured wiring
%
$3,00041.0%
15Insulation
%
$9,00044.0%
16Drywall hang
%
$15,00049.0%
17Drywall tape & finish
%
$9,00052.0%
18Exterior siding / brick / stucco
%
$24,00060.0%
19Fascia, soffit & gutters
%
$6,00062.0%
20Stair installation
%
$3,00063.0%
21Exterior paint
%
$6,00065.0%
Draw 04 — Interior Finishes · 25%
22Interior doors & trim
%
$9,00068.0%
23Cabinets
%
$12,00072.0%
24Countertops
%
$6,00074.0%
25Interior paint
%
$9,00077.0%
26Tile & flooring
%
$9,00080.0%
27Hardwood / carpet flooring
%
$6,00082.0%
28Plumbing trim & fixtures
%
$6,00084.0%
29Electrical trim & fixtures
%
$6,00086.0%
30HVAC trim & startup
%
$6,00088.0%
31Appliances
%
$6,00090.0%
Draw 05 — Final & CO · 10%
32Mirrors, shelving & hardware
%
$6,00092.0%
33Exterior concrete (driveway/walks)
%
$9,00095.0%
34Landscaping & grading
%
$9,00098.0%
35Final clean & punch list
%
$6,000100.0%
Total100.0%$300,000

This is a general planning template, not an official lender draw schedule — it's meant to help you think through how your budget breaks down by phase before you apply. New construction loans through BldFi typically fund in five broader milestone draws; see that schedule. Your actual draw structure is finalized with your lender based on your specific project.