Loan Terms

Loan amount
$250K – $5M
LTC up to
90%
LTV up to
70% of ARV
Rate from
10.5% / year
Loan term
12 – 24 months
Payment type
Interest only
Origination fee
1 – 2 points
Prepayment
None with many lenders
Time to close
10 – 14 days typical
Apply for this loan

No hard credit pull at inquiry stage. Response within 1 business day.

Draw Schedule

How the draw process works.

Funds release in milestone-based draws as construction progresses and inspections are completed. You only pay interest on funds drawn — not the full commitment.

Draw 01
Foundation & Site Work
15%
Land clearing, foundation pour, underground utilities
Draw 02
Framing & Rough-In
25%
Framing complete, roof decked, rough plumbing, HVAC, electrical
Draw 03
Drywall & Mechanicals
25%
Insulation, drywall hung and taped, mechanical trim-outs
Draw 04
Interior Finishes
25%
Flooring, cabinets, paint, fixtures, appliances installed
Draw 05
Final & CO
10%
Punch list complete, certificate of occupancy issued

Draw percentages are typical defaults. BldFi works with borrowers to customize schedules to match actual project phases.

Full line-item breakdown

Every construction category rolls up into one of the five draws above — grouped and shaded here to show which draw each line item is allocated to.

#Line item% of budget
Draw 01 — Foundation & Site Work · 15%
1Site work & grading3%
2Footings3%
3Foundation / slab9%
Draw 02 — Framing & Rough-In · 25%
4Framing — walls6%
5Framing — roof4%
6Roof decking & sheathing3%
7Roofing (materials & install)3%
8Windows2%
9Exterior doors1%
10House wrap & exterior sheathing2%
11HVAC rough-in2%
12Plumbing rough-in1%
13Electrical rough-in1%
Draw 03 — Drywall & Mechanicals · 25%
14Low-voltage / structured wiring1%
15Insulation3%
16Drywall hang5%
17Drywall tape & finish3%
18Exterior siding / brick / stucco8%
19Fascia, soffit & gutters2%
20Stair installation1%
21Exterior paint2%
Draw 04 — Interior Finishes · 25%
22Interior doors & trim3%
23Cabinets4%
24Countertops2%
25Interior paint3%
26Tile & flooring3%
27Hardwood / carpet flooring2%
28Plumbing trim & fixtures2%
29Electrical trim & fixtures2%
30HVAC trim & startup2%
31Appliances2%
Draw 05 — Final & CO · 10%
32Mirrors, shelving & hardware2%
33Exterior concrete (driveway/walks)3%
34Landscaping & grading3%
35Final clean & punch list2%
Run this against your own budget
Why BldFi

Built for new construction projects.

High LTC means less cash out of pocket

Up to 90% of total project cost — so you preserve capital for your next deal while the lender carries the heavy load.

Draws typically released in 3–5 business days

Submit your draw request, the lender completes the inspection, funds are released. No waiting weeks for bank committees to convene.

Customizable draw schedules

Standard five-phase draws or a schedule built around your actual project milestones. Your build, your timeline.

Repeat borrower pipeline

Close your first deal through BldFi and your next one gets priority service and reduced documentation — and many of our lender partners offer preferred rates to repeat borrowers.

Eligibility

What you'll need to qualify.

Lenders look at the deal and the borrower together. Strong projects with solid equity and an experienced team get to yes faster. Exact requirements vary by lender.

Minimum 640 FICO — higher scores unlock better rates
10% borrower equity minimum at project cost
Detailed construction budget with contractor bids
Approved plans and permits (or in-process)
Licensed general contractor with verifiable experience
Entity borrowing preferred (LLC or corporation)
Prior construction experience helpful — first-timers considered with stronger equity
Project located in a market our lender partners serve
FAQ

New Construction loan questions.

Ready to fund your new construction project?

Submit your project details today and hear back from our team within 48 hours.

Start Your Application